“How long will my interiors take?” is one of the first questions every homeowner asks. Delays are also one of the biggest fears. You may be paying rent and EMI at the same time, or planning a housewarming date.
Here is a clear, step-by-step interior design timeline, from the first call to the day you move in. This is how we work at Sreesai Interiors, and how the woodwork in most of our homes is completed in 25–30 days after work starts.
The full timeline at a glance
| Step | What happens | Time |
|---|---|---|
| 1. First call or WhatsApp | You share your home type, area and budget | Day 1 |
| 2. Free site visit | Measurements, your needs, first ideas | Within 1 day |
| 3. Quotation | Clear pricing with 2–3 material options | Same day as visit |
| 4. Design and approval | You review, request changes, then approve | Usually 1–2 days to decide |
| 5. Materials arranged | We arrange materials before taking any advance | A few days |
| 6. Execution | Carpentry, false ceiling, electrical, painting | Woodwork in about 25–30 days; electrical and painting depend on the home |
| 7. Handover | Final check, deep cleaning, keys back to you | Last day |
Step 1: The first conversation
You call or WhatsApp us and tell us about your home: 2BHK, 3BHK or villa, the area, your possession date and a rough budget. Sharing your floor plan here saves time later.
Step 2: Free site visit within 1 day
We visit your home, take measurements and understand how your family lives. Do you cook a lot? Do you need a study corner? Do elders need easy-access storage? This is also when we share first ideas.
Step 3: Same-day quotation
You get a clear quotation the same day, with 2–3 material options. No guessing, and no “we’ll tell you the final price later”.
Step 4: Design and approval
We share a clear design plan so you know exactly what will be built. You can ask for changes until you’re happy. Most customers approve within 1–2 days.
Step 5: Materials first, then the advance
We arrange your materials first, without any advance. Work starts after a 40% advance, and the rest is paid in 4–5 stages as work progresses. This protects you and keeps the project moving.
Step 6: Execution, week by week
For a typical full 2BHK, the work usually goes like this:
- Week 1: Carpentry begins; false ceiling framework and electrical points are marked.
- Week 2: Kitchen and wardrobe units take shape.
- Week 3: Shutters, laminates, TV unit and remaining storage.
- Week 4: Hardware, fittings and woodwork touch-ups.
False ceiling finishing, electrical work and painting continue alongside and after the woodwork. How long they take depends on the size of your home and the work involved, so we give you a clear timeline with your quote.
Because one in-house team handles carpentry, false ceiling, electrical and painting, there is no waiting for different vendors. That is the main reason our projects finish on time.
Step 7: Handover with deep cleaning
We inspect every room with you, fix any small issues and deep-clean the home. You get a ready-to-move-in home, plus 5 years of free service for hardware and door problems.
How long do smaller jobs take?
- Modular kitchen only: about 1 week to 10 days
- Wardrobes only: about 1 week to 10 days
- False ceiling with lighting: depends on the area; we share the timeline in your quotation
What causes interior delays (and how to avoid them)
- Changing the design mid-way. Finalise the design before work starts.
- Too many vendors. Separate carpenters, electricians and painters wait on each other. One team avoids this.
- Late material decisions. Choose laminates and colours during the design stage.
- Society permissions. Check your apartment’s work timings and rules early.
Frequently asked questions
Can interiors be done before possession?
Planning and design can start before possession. Execution starts once you have access to the flat.
Can I stay in the house during the work?
For small jobs like a kitchen or wardrobes, yes. For a full home, it’s easier to move in after handover.
Have a move-in date in mind?
Tell us your possession date and we’ll plan backwards from it. See how our full home interiors work, or read the 2BHK cost guide.